Connecticut Supreme Court Upholds Trial Court’s Finding That Surety Had Not Proven Indemnification and Had Breached Its Covenant of Good Faith and Fair Dealing

publication date: Jan 11, 2004
View a Printer Friendly version of this page, allowing you to print the page. Send a summary of this page to someone via email.
Mercede, a general contractor hired to construct an assisted living facility in Stamford, Connecticut, furnished the owner of the project a labor and materials payment bond. After the steel subcontractor filed for bankruptcy, PSE, the steel erection sub-subcontractor, filed suit against Mercede and the surety for the balance of the original contract plus reimbursement for extras. The surety ultimately settled with PSE even though Mercede disputed PSE’s claims for extra work and Mercede had not been paid by the owner for the balance of contract sums owed PSE. Mercede refused to pay the surety under the indemnity agreement. At trial, the surety had not proven its claim for indemnification and this appeal followed.


This page is available to members only.
To subscribe, click here

Construction Claims Online Features and Benefits


Whether your role in the construction claims process is as a building owner, designer, contractor, facility manager, attorney or consultant, you will want to keep up with the latest developments in construction law, federal and state policy, construction process and best practices.

Whether you sign up for our free or paid content, Construction Claims Online provides information you need to achieve successful outcomes for project issues and your clients' best interests.


Avoid costly errors by understanding how the boards and courts look at typical disputes situations.
Achieve successful project outcomes.
Defend against unsubstantiated claims.
Reduce or eliminate risks.