S. D. Deacon Corporation
of Washington
v. Gaston Brothers Excavating, Inc.
No. 61702-8-1
May 11, 2009
Overview
A Washington court has
ruled that a "frivolous lien" procedure should not be used to defeat a
contractor's claim without a hearing on the merits. The summary release of a
mechanic's lien should be granted only when there is no possibility of
sustaining the lien.
Background
S. D. Deacon
Corporation of Washington was the general
contractor for construction of a fitness center in Seattle. Deacon requested quotations for site
work from Gaston Brothers Excavating Inc., which submitted a bid of $49,000 for
the footing work. Three days later, Gaston submitted a bid of $63,000 for a
crushed glass moisture barrier.
Deacon sent a
letter to Gaston agreeing to award a subcontract for $112,000. Gaston started
work. The subcontractor submitted a progress payment request, which reflected a
total subcontract price of $112,000. Deacon paid the requested amount, less 10
percent retainage. Deacon then sent Gaston a written subcontract agreement
indicating a fixed price of $63,000.
Gaston
continued work despite the disagreement over price. Deacon made another payment
of $9,891 to the subcontractor. Deacon then issued a unilateral, deductive
change order reducing the subcontract price to $54,100, the precise amount
Deacon had already paid to Gaston. Deacon refused to make further payment.
Gaston filed
a timely mechanic's lien on the project property for $43,191. Deacon filed a
motion for the summary removal of a frivolous lien, a procedure authorized by
the Washington
lien statutes, RCW 60.04.081. Deacon contended the lien was frivolous because
Gaston had been paid in full. A trial court agreed and released the lien.
Gaston appealed.
The Ruling
The Court of
Appeals of Washington
said the frivolous lien procedure should not be misused to deprive a lien
claimant of a hearing on the merits of its claim. A lien should be removed as
frivolous only after a factual finding that it is devoid of merit and there is
no possibility of sustaining the lien. No such finding existed in this case.
And, said the court, there was ample evidence to the contrary.
To begin, the
parties had a legitimate dispute regarding the subcontract price. Deacon now
said that the second quotation of $63,000 covered all subcontract work; its
earlier reference to an $112,000 subcontract was an error. Gaston pointed out
that each of its two price quotations expressly referred to separate, discrete
portions of the work.
Additionally,
there were no invoices or other documentation supporting Deacon's deductive
change order reducing the price to the precise amount paid to Gaston. And,
there was no accounting for the 10 percent retainage Deacon withheld from the
first progress payment. These factual disputes should have been given a full
hearing. The lien should not have been removed in summary fashion.
Conclusion
Many state
lien statutes include procedures for removal of a frivolous lien. The
procedures are most commonly, and appropriately, used in situations in which
the lienor has clearly failed to comply with the statutory requirements for
maintaining a mechanic's lien. Removal does not address the merits of the
underlying claim, only statutory compliance and the right to secure a potential
obligation with a lien on the property.
Case
participants: For S. D. Deacon Corp. of Washington: John Todd Henry.
For Gaston Brothers
Excavating, Inc.: Sage Andrew Linn.
Before:
Judges Becker, Dwyer and Grosse.
Opinion by: Judge Becker.
Outcome: Summary removal of mechanic's lien reversed. Case
remanded.
Click here to view the complete opinion.