Wayne Knorr, Inc. v. Pennsylvania Department of Transportation
No. 1593 C.D. 2008
May 14, 2009
Overview
A
Pennsylvania
court has ruled that a contractor could not recover extended home office
overhead for a period of owner-caused delay. Mark-ups on extra, force account
work had already compensated the contractor for that cost.
Background
The
Pennsylvania Department of Transportation awarded a fixed-price contract to
Wayne Knorr Inc. to improve a section of two-lane state highway in Armstrong County by adding a third, truck-climbing
lane. The contract required substantial completion within 368 days of notice to
proceed.
Knorr encountered problems with slope instability in the area where the third lane
was being added. PennDOT was slow to respond to the problem, forcing Knorr to
alter the sequence of its work. PennDOT subsequently authorized the repair and
stabilization of the slope, directing Knorr to perform the extra work on a
time-and-materials, or "force account," basis. The contract specifications
stipulated mark-ups on all force account costs: 40 percent on labor, 25 percent
on materials and five percent on equipment.
Knorr
completed the project 116 days after the original completion deadline and filed
a claim for its extra costs, including delay and disruption damages. The
Pennsylvania Board of Claims determined that PennDOT was responsible for 72
days of delay on the schedule's critical path.
The board ruled that Knorr was entitled to
force account compensation for the extra work it performed, as well as the
delay and disruption it experienced. The contractor was awarded, on a force account
basis, the increased costs it incurred in working out of sequence; moving crews
and equipment from place to place. But, the Board refused to award Knorr the
$101,228 it claimed in extended home office overhead-those expenses were
covered by the mark-ups on the force account direct costs. Knorr appealed.
The
Ruling
The Commonwealth Court of Pennsylvania said
the contract specifications clearly intended the mark-ups on force account work
to compensate the contractor for any extended home office overhead it might
incur. The mark-ups covered "all administration, general superintendence, other
overhead, bonds, insurance, anticipated profit, and use of small tools and
equipment for which no rental is allowed." Separate recovery of home office
overhead would be duplicative.
"Because
Knorr's expert utilized the mark-ups contemplated in [the specifications] in
calculating Knorr's delay damages, which include an allowance for extended home
office overhead, Knorr could not also recover extended home office overhead
costs as a separately delineated delay damage claim. No error is apparent in
the Board's decision to reject Knorr's extended overhead claim, which would
amount to a double recovery for Knorr."
Conclusion
The contractor characterized this claim as
one for "extended," rather than "unabsorbed," home office overhead. Unabsorbed
overhead is defined as home office expenses not absorbed by a fixed-price
contract at the anticipated rate because contract performance (and therefore
contract billing) was extended over a longer period of time due to project
owner suspension of the work. As with the extended overhead in this case,
unabsorbed overhead cannot be recovered when the performance period was
extended because of changed or extra work and the contractor was compensated
for direct costs plus overhead.
C. B. C. Enterprises, Inc. v. United States, 978 F.2d 669
(Fed. Cir. 1992).
Case participants: For Wayne Knorr, Inc.: E. James Reynolds, Jr.
For PennDOT: Christopher F. Wilson.
Before: Judges
McGinley, Simpson and Kelley.
Opinion by: Judge Simpson.
Outcome: Board of Claims judgment affirmed.
Click here to view the complete opinion.