Liquidated damages for contractors' late completion of projects frequently prove contentious. A contractor is aware of the stipulation when signing the contract. But when faced with the withholding of a substantial liquidated damages assessment, the contractor usually argues the delay was not its fault and the liquidated damages clause is unenforceable.
This was the scenario in a recent case in which a power plant contract called for liquidated damages of $49,000 per day for each of three turbines. Even after being credited for excusable delay, the contractor faced more than $26 million in liquidated damages withholding. The contractor argued this was an unenforceable penalty -- the liquidated damages assessment greatly exceeded the project owner's actual cost of late completion and provided a windfall. The contractor's argument failed and the owner kept the liquidated damages.
Other cases reported this week involved bid responsiveness and the proper notice of appeal on a federal claim. A Florida court ruled that the failure to list prior projects rendered a low bid nonresponsive. And, the Armed Services Board said no particular form or language is needed for a contractor to invoke its appeal rights.
This page is available to members only. To subscribe, click here
Construction Claims Online Features and Benefits
Whether your role in the construction claims process is as a building owner, designer, contractor, facility manager, attorney or consultant, you will want to keep up with the latest developments in construction law, federal and state policy, construction process and best practices.
Whether you sign up for our free or paid content, Construction Claims Online provides information you need to achieve successful outcomes for project issues and your clients' best interests.
Avoid costly errors by understanding how the boards and courts look at typical disputes situations. Achieve successful project outcomes. Defend against unsubstantiated claims. Reduce or eliminate risks.