EDITOR'S NOTES | Issue 7-50

publication date: Dec 20, 2009
View a Printer Friendly version of this page, allowing you to print the page. Send a summary of this page to someone via email.
When a subcontractor completes its work, it is not unusual for unresolved disputes with the prime contractor to linger. The subcontractor may demand release of final payment, but the prime will understandably be reluctant to part with the funds when unresolved claims remain on the table. The subcontract may or may not address this situation. And in many jurisdictions, prompt payment statutes impose penalties for refusing to release final payment.

A California contractor recently faced this dilemma. A subcontractor asserted extra work claims against the contractor totaling half a million dollars. But, the sub completed its work and the public project owner paid the contractor for that work. A prompt payment statute required release of retainage to the subcontractor within seven days. Fortunately for the contractor, the statute provided a safe harbor when there was a bona fide dispute.

Other cases this week involved a contractor's right to recover against a subcontractor's performance bond and the impact of a bidder's failure to fully complete a questionnaire. The contractor lost its bond rights because it failed to declare a default and notify the subcontractor's surety. And, the bidder was disqualified because of its lack of attention to detail.

Your next issue of Construction Claims Advisor will arrive on Jan. 3, 2010. WPL Publishing wishes you a very happy holiday season and a prosperous new year.



This page is available to members only.
To subscribe, click here

Construction Claims Online Features and Benefits


Whether your role in the construction claims process is as a building owner, designer, contractor, facility manager, attorney or consultant, you will want to keep up with the latest developments in construction law, federal and state policy, construction process and best practices.

Whether you sign up for our free or paid content, Construction Claims Online provides information you need to achieve successful outcomes for project issues and your clients' best interests.


Avoid costly errors by understanding how the boards and courts look at typical disputes situations.
Achieve successful project outcomes.
Defend against unsubstantiated claims.
Reduce or eliminate risks.