EDITOR'S NOTES | Issue 8-20

publication date: May 15, 2010
View a Printer Friendly version of this page, allowing you to print the page. Send a summary of this page to someone via email.

Delay and disruption can be two of the costliest occurrences on a construction project. If a contractor is forced to work out of sequence, in a stop-and-start fashion, or in a congested work area, labor costs can increase greatly. Known as “lost productivity” or “labor inefficiency,” this element of recovery is significant. But, it is also difficult to quantify and prove.

A recent case involved a multiple prime contract project in Tennessee. The public project owner and its construction manager failed to properly schedule and coordinate the work of the various trade contractors. Two contractors sought to recover lost productivity, one using the “measured mile” method and the other using the “modified total cost” method. The project owner argued that these forms of quantification were not sufficiently precise and were impermissible.

Other cases this week address compliance with a specified dewatering method and a “requirements” type contract for construction services. A contractor’s attempted deviation from the dewatering spec was not justified by an alleged differing site condition. And, a government agency could divert required work to other contractors because the amounts of the orders exceeded a limitation clause in the contract.



This page is available to members only.
To subscribe, click here

Construction Claims Online Features and Benefits


Whether your role in the construction claims process is as a building owner, designer, contractor, facility manager, attorney or consultant, you will want to keep up with the latest developments in construction law, federal and state policy, construction process and best practices.

Whether you sign up for our free or paid content, Construction Claims Online provides information you need to achieve successful outcomes for project issues and your clients' best interests.


Avoid costly errors by understanding how the boards and courts look at typical disputes situations.
Achieve successful project outcomes.
Defend against unsubstantiated claims.
Reduce or eliminate risks.