When a project owner issues a directive that the contractor considers a change in the scope of work, the contractor does not have many options. The practical necessities of the project – and the contract documents themselves – require the contractor to proceed with the work. The best the contractor can do is to preserve its rights to pursue a claim for a constructive change in the contract.

A recent case illustrates the hurdles an owner can place in the contractor’s path. A federal agency used a changes clause that required the contractor to submit an itemized change order cost proposal. The agency then responded with a “settlement by determination” – a unilateral contract modification in which the government set the price adjustment at the amount it considered adequate.

Other cases this week involved the optional use of a prevailing wage law and the treatment of subcontractor experience when evaluating proposals. A school board could elect to impose prevailing wage standards even though school projects were expressly exempt from the state wage statute. And, agency evaluators could not treat subcontractor experience in an inconsistent manner.



This page is available to members only.
To subscribe, click here

Construction Claims Online Features and Benefits


Whether your role in the construction claims process is as a building owner, designer, contractor, facility manager, attorney or consultant, you will want to keep up with the latest developments in construction law, federal and state policy, construction process and best practices.

Whether you sign up for our free or paid content, Construction Claims Online provides information you need to achieve successful outcomes for project issues and your clients' best interests.


Avoid costly errors by understanding how the boards and courts look at typical disputes situations.
Achieve successful project outcomes.
Defend against unsubstantiated claims.
Reduce or eliminate risks.