EDITOR'S NOTES | Issue 8-32

publication date: Aug 15, 2010
View a Printer Friendly version of this page, allowing you to print the page. Send a summary of this page to someone via email.

Public construction contracts are sometimes subject to change order limitations. These may be imposed by statute, regulation or the contract itself. The purpose is to protect the project budget and the integrity of the public procurement process by limiting the expansion of the contractual scope of work. If the estimated cost of a change order exceeds a stipulated percentage of the original contract price, the additional work must be put out to bid.

Change order limitations can lead to shenanigans, however. In a recent California case, a public project owner and its construction manager tried to circumvent a 10 percent limit in a site work contract in order to avoid the delay of competitive bidding. New grading work was added to the general building contract and then the building contractor subbed the work to the site contractor. The purported subcontract was ruled a sham.

Other cases this week involved a bidder’s false statements during the prequalification process and a contractor’s attempt to assess delay damage backcharges against a subcontractor’s performance surety. The public project owner had been aware of the bidder’s misrepresentations and had discretion to award the contract nonetheless. And, the contractor could not backcharge the sub’s surety due to lack of timely notice of default.



This page is available to members only.
To subscribe, click here

Construction Claims Online Features and Benefits


Whether your role in the construction claims process is as a building owner, designer, contractor, facility manager, attorney or consultant, you will want to keep up with the latest developments in construction law, federal and state policy, construction process and best practices.

Whether you sign up for our free or paid content, Construction Claims Online provides information you need to achieve successful outcomes for project issues and your clients' best interests.


Avoid costly errors by understanding how the boards and courts look at typical disputes situations.
Achieve successful project outcomes.
Defend against unsubstantiated claims.
Reduce or eliminate risks.