Search
Events Calendar
«  »
SMTWTFS
 12345
6789101112
13141516171819
20212223242526
2728293031 

EDITOR'S NOTES | Issue 8-49

publication date: Dec 19, 2010
View a Printer Friendly version of this page, allowing you to print the page. Send a summary of this page to someone via email.

Construction contracts can be voluminous and complex. Sometimes the various provisions don’t fit together properly. They may even be in conflict. Faced with these ambiguities, courts will resort to “extrinsic evidence” – guidance not found in the language of the contract itself.

In a recent Tennessee case, an early completion incentive bonus clause stipulated a calendar date, but was silent regarding any extension of that date. A separate contract provision called for extending the performance period to the extent the contractor encountered excusable delay. Did the excusable delay provision extend to the early completion bonus deadline? The court was forced to examine extensive correspondence between the state highway department and federal funding sources.

Other cases this week involved a limitation of subcontracting clause and the right to recover payment in quantum meruit. Although a disappointed offeror alleged there was no way an awardee could comply with the subcontracting limitation, there was nothing in the awardee’s proposal that took exception to the requirement. And, payment was recovered even though the claimant performed no work with its own forces.



This page is available to members only.
To subscribe, click here

Construction Claims Online Features and Benefits


Whether your role in the construction claims process is as a building owner, designer, contractor, facility manager, attorney or consultant, you will want to keep up with the latest developments in construction law, federal and state policy, construction process and best practices.

Whether you sign up for our free or paid content, Construction Claims Online provides information you need to achieve successful outcomes for project issues and your clients' best interests.


Avoid costly errors by understanding how the boards and courts look at typical disputes situations.
Achieve successful project outcomes.
Defend against unsubstantiated claims.
Reduce or eliminate risks.