In a reversal of its previous opinion, a full panel of appellate judges (sans one) opines that a contractor cannot recover delay damages from a utility for wrongly marked lines if the utility is not a party to the construction contract.
A contractor’s increased performance costs can be levied against a government agency that constructively suspending the contractor’s work through a work directive. However, the amount has its limits—field overhead mark-ups cannot be included.
A state appellate court largely ignores a contractor’s argument that a project engineer’s late response for approval on substitute parts was the reason for late completion. The court upholds a lower court’s ruling for liquidated damages.