Even though drawings for certain trade work omit a work requirement, the specifications mandate it. The contract documents, when read as a whole, require the work described in the specifications.
A settlement agreement for changed work grants the contractor an extension of time, but none of that extension is attributable to weather delays. The contractor may have reserved its claim for weather delays to critical activities pushed back into the winter season by the changed work.