|
November 24, 2003
Improper Inspection Paves the Way for Recovery on Bike Path
Unanticipated mobilization costs allowed as a result of changes and differeing site conditions.
On a Federal Highway Administration bike path project, the Court of Federal Claims awarded a contractor extra costs resulting from improper inspection, which breached the governments implied duty to cooperate. Although the contractor was awarded only 25% of its total claim, the court recognized the concept of "unanticipated mobilization" costs as well as declaring that the government project engineer, by conduct, had actual authority to bind the government.
Subscribers: click here for the full story
 Non-Subscribers: click here to subscribe
|