Home | Login | About Us | Contact Us | Site Map | Privacy Policy
Construction Claims Online The Leading Web Resource for Those Involved in the Business of Avoiding, Managing, and Resolving Construction Disputes
Search This Site

Advanced Search

Browse Claims Library


Subscribe
Current Issue
Past Issues
Sample Issue
Bookstore
Directory
Links
Press Releases
Editorial Calendar
Editorial Board

FREE NEWSLETTER!

Volume 5 - Number 11 | March 12, 2007

EDITOR'S NOTES
Service-oriented companies often tout that the customer is always right. This approach may work if you are ordering a meal at a fast food establishment, but in the construction industry, a better motto is this: “Get it in writing!” This week’s set of cases deal with problems that arise when the written word (or lack of it) is called into question.

In our first case, a project owner argues that the arbitration clause in its contract is void once it terminates the contract for default. Not so, says a Florida appellate court. Because the project was substantially complete when the owner fired its contractor, the conflict management portion of the contract still stands.

Next, a contractor on a government project must proffer written verification to prove that the contract was altered to allow a payment adjustment for liquidated damages. Verbal agreements aren’t enough.

Even when a written agreement is in place, it is often open to interpretation. In our third case, a state high court considers whether a general contractor’s CGL policy covers faulty workmanship of its subcontractor.

This issue concludes with a look at what happens when schedulers misappropriate lag time in their schedules. The article, by Jens Baker, offers some ways to avoid this problem.


CONTRACTOR’S ARBITRATION RIGHTS SURVIVED DEFAULT TERMINATION
A project owner cannot terminate a substantially completed project for default, then argue that the contract’s mediation and arbitration clauses are no longer valid because of the termination.

LIQUIDATED DAMAGES AGREEMENT REQUIRED CONTRACT MODIFICATION
When a contractor negotiates a payment adjustment for liquidated damages on a government project, it needs to procure written documentation from the contracting officer to support the contract change. Otherwise, the adjustment is unenforceable.

FAULTY WORKMANSHIP CONSTITUTES “OCCURENCE” AND “PROPERTY DAMAGE” UNDER “MODERN” CGL POLICY
By Rob Carter
In a case of first impression, a state high court concludes that damage caused by a subcontractor’s faulty window installation is a coverable “occurrence” on a general contractor’s commercial general liability policy.

LAZY CONCRETE
By Jens Baker
Lazy concrete is not a concrete mix that refuses to cure. Rather, it’s a phenomenon that occurs when schedulers fail to properly program cure time into the schedule. Guest columnist Jens Baker offers the scheduling cure-all to combat this problem.