SUB BOUND BY PRIME CONTRACTOR’S CLAIM REMEDIES

Court of Appeals of North Carolina

A prime contractor has the right to pursue claim remedies against an owner for alleged delays before its subcontractor can pursue litigation against the contractor for the same issues, says a North Carolina court. If the dispute resolution mechanism in the prime contract is incorporated into the subcontract, the subcontractor must abide by the prevailing contract.