Home | Login | About Us | Contact Us | Site Map | Privacy Policy
Construction Claims Online The Leading Web Resource for Those Involved in the Business of Avoiding, Managing, and Resolving Construction Disputes
Search This Site

Advanced Search

Browse Claims Library


Subscribe
Current Issue
Past Issues
Sample Issue
Bookstore
Directory
Links
Press Releases
Editorial Calendar
Editorial Board

FREE NEWSLETTER!

Volume 5 - Number 26 | June 25, 2007

EDITOR'S NOTES
Arbitration clauses are standard in most construction contracts. But, what happens when a party argues that the contract as a whole is illegal? Does the arbitration clause still stand? Who decides if the contract is illegal—an arbitrator or the courts? In February 2006, the U.S. Supreme Court released an opinion clarifying these questions. Buckeye Check Cashing, Inc. v. Cardegna, 546 U.S. 440 (2006). In Buckeye, it reiterated a previous case in which it established that an arbitration clause is severable from the rest of the document. It said, “[R]egardless of whether the challenge is brought in federal or state court, a challenge to the validity of the contract as a whole, and not specifically to the arbitration clause, must go to the arbitrator.” The Buckeye decision provides the basis for this week’s first case, which involves the appeal of a payment dispute between a project owner and its contractor.

This week’s other two cases center around delay damages. Can a contractor on a non-federal project use its in-house scheduled completion date as the basis for determining delay damages? Only if it’s the date listed on the contract or the date both parties agreed upon via a contract modification, says a California appeals court. (Federal projects are governed by a different standard.) And, can a contractor assess delay damages against a subcontractor if the project owner does not also assess damages on the contractor for that portion of the work? Not unless it’s in the contract, rules a federal appeals court.


ARBITRATOR MUST RULE FIRST ON LEGALITY OF CONTRACT
A contractor gets a second look at its claim against an owner after the U.S. Supreme Court rules that an arbitration clause is severable from the rest of the contract when determining the underlying contract’s legality. In this instance, an arbitrator, not the court, has the first opportunity to determine if the contract is illegal.

CONTRACTOR’S SCHEDULE DID NOT ALTER CONTRACT COMPLETION DATE
A contractor cannot use a self-imposed completion date to calculate damages for owner-caused delays. Damages are assessed from the date stated on the contract, not the date the contractor originally thought it could complete the project.

COURT ADDRESSES NO-DAMAGE-FOR-DELAY CLAUSE AND LIQUIDATED DAMAGES PASS-THROUGH
If a project owner does not assess delay damages against its contractor, the contractor cannot collect liquidated damages from its subcontractor for those delays, rules a federal appeals court.