June 25, 2007
CONTRACTORS SCHEDULE DID NOT ALTER CONTRACT COMPLETION DATE
Court of Appeal of California, Third Appellate District
A contractor cannot use a self-imposed completion date to calculate damages for owner-caused delays. Damages are assessed from the date stated on the contract, not the date the contractor originally thought it could complete the project.