|
November 5, 2007
EDITOR'S NOTES
Sometimes a project will be ruled a success despite the contractors deviations from specifications and/or testing requirements. On a paving project, the contractor failed to follow pre-installation testing procedures on asphalt. The completed work was deemed acceptable, but because of the lapse in protocol, the public owner had to perform its own tests to ensure material compliance. As such, the owner was entitled to liquidated damages for the extra costs associated with testing and administration, plus a 50 percent price reduction on materials, as stated in the contract.
Contract specifications and an Order of Precedence clause are at the heart of the second case, which involves a contractor and the Army Corps of Engineers in a dispute about drawings and specifications.
Patterns of conduct that conflict with contract requirements can be dicey from a legal standpoint. Courts must often sort out which code will prevail. In this weeks third case, a court decides that actions speak louder than words.
Finally, we continue our series on the AACE Internationals recently released Recommended Practice 29R-03Forensic Schedule Analysis. This week, John Livengood summarizes the eight methods of forensic delay analysis and offers his expert opinion on each method.
Subscribers: click here for the full story
 Non-Subscribers: click here to subscribe
|