March 20, 2006
PAY-IF-PAID EFFECT TRICKLES DOWN WHEN OWNER GOES BELLY UP
U.S. Court of Appeals, 10th Circuit
MidAmerica Construction Management, Inc. v. MasTec North America, Inc., and Renegade of Idaho, Inc.
No. 04-6231 February 8, 2006
Overview
When the project owner PathNet Inc. filed for bankruptcy, subcontractor MidAmerica Construction of Oklahoma sued contractors Mastec North America of Florida and Renegade of Idaho Inc. to get paid for work it had performed. The courts, however, determined that a pay-if-paid clause, under Texas and New Mexico law, meant that the contractors did not have to pay MidAmerica if they themselves had not been paid by PathNet.
Background
PathNet hired Renegade to help build the New Mexico and Texas portions of a fiber optic network. MasTec subsequently purchased Renegade. The defendants hired MidAmerica for work performed in January and February of 2001 and made an initial $127,000 payment to MidAmerica in March 2001. PathNet filed for bankruptcy in April 2001 and MasTec refused to make any further payments to MidAmerica, asserting it had not received payment from PathNet for the work MidAmerica had performed. MidAmerica sued the defendants in U.S. District Court for the Western District of Oklahoma for $1.9 million.
The district court denied MidAmericas motion for partial summary judgment and granted the defendants counter-motion for summary judgment, holding that a provision in the subcontract provided that all payments to the subcontractor by the contractor are expressly contingent upon and subject to receipt of payment for the work by contractor from owner. The court said that unless or until PathNet paid the defendants, they had no obligation to pay the plaintiff. It also found that a termination clause in the subcontract barred MidAmericas claims for breach of contract.
The Appeals Courts Ruling
The appeals court affirmed the district courts summary judgment. It concluded that the pay-if-paid clause is enforceable under both Texas and New Mexico law, making PathNets payment of defendants a condition precedent to defendants obligation to pay plaintiff. The appeals court noted that construction contracts often contain provisions such as pay-when-paid and pay-if-paid, but said they refer to distinct types of contractual clauses. The appeals court said that a typical pay-when-paid clause might read: Contractor shall pay subcontractor within seven days of contractors receipt of payment from the owner. Such a clause, it said, does not create a condition precedent to the obligation to ever make payment and it does not expressly shift the risk of the owners nonpayment to the subcontractor. However, a typical pay-if-paid clause might read: Contractors receipt of payment from the owners is a condition precedent to the contractors obligation to make payment to the subcontractor; the subcontractor expressly assumes the risk of the owners nonpayment and subcontract price includes this risk.
Conclusion
The subcontract contained the necessary language to make PathNets payment to defendants a condition to their obligation to pay MidAmerica. And although the supreme courts of both states had not definitively determined where to draw the line between pay-if-paid and pay-when-paid, the U.S. appeals court determined it appears that case law in both states would interpret pay-if-paid as an enforceable clause.
Case participants: Albert W. Murry (Murry Cox & Murry) for plaintiff-appellant.
Henry D. Hoss (McAfee & Taft) for defendants-appellees.
Before: Judges Ebel, Tymkovich and Browning.
Opinion By: Judge Ebel.
Decision: Affirmed.
|